A control room log should help controllers maintain situational awareness across multiple shifts and rotations. Situational awareness occurs when a controller understands the current state of the system and anticipated future state. Situation awareness enables sound decisions and work priority. Additionaly, a useful log carries operating context across shifts, creates a record that can be used to improve performance, and provides operating history for other stakeholders who require the information.
When operating context lives only in conversation, it can be lost at shift change. Before the 2010 pipeline rupture near Marshall, Michigan, the operator’s procedure required specific information to be exchanged at shift change, but no written record of it. The incoming shift lead later said he hadn’t been told about the shutdown, the pending startup, or the leak detection alarm (NTSB PAR-12/01). The causes of that accident were much broader than one handover, but the detail shows what a log is for.
The Control Room Management (CRM) Rule never uses the word “logbook.” Still, 49 CFR 192.631 and 49 CFR 195.446 require a method of recording shift changes and handovers, procedures defining what information is exchanged, and records that demonstrate compliance. The First Edition of API 1168, published in September 2008 is incorporated by reference. While the Third Edition of API RP 1168, published in May 2026, isn’t incorporated by reference, it reflects a broader move from having a CRM program to demonstrating that it works (EnerSys review).
The practices below start from one principle: write each entry for the next person who needs to understand the operating state and take action on it. Records created with that purpose also hold up as evidence of a well-run program.
1. Define what deserves an entry
Controllers need a shared understanding, written into procedure, of which events belong in the log. Typical categories include:
- Shift handovers and temporary relief
- Abnormal operating conditions
- Field communications that affect operations
- Equipment outages and operating restrictions
- Alarm inhibits and points taken off scan
- Deviations from procedure
- Direction that changes or supersedes a controller’s technical actions
- Pending work and unresolved issues
The question for each is whether it affects operating decisions, responsibilities, or follow-up.
Operational benefit: Consistent expectations help the next controller separate normal conditions from exceptions and see which constraints remain in effect. Expectations that exist only as habit also don’t hold up during an inspection. PHMSA has cited an operator whose “trouble log” wasn’t required by its procedures, and another whose procedure didn’t say to log manually confirmed field data or where to log it. For direct and supersede actions, FAQ J.05 already expects records, and API 1168 Third Edition recommends defining what gets documented when that authority is used.
2. Make every entry useful on its own
A good entry answers who, what, where, and when. It also explains what was done, the current status, and what still needs attention. The reader shouldn’t have to find the person who wrote it.
Consider these two illustrative entries:
Weak entry: “Field called about pressure issue. Checked it. Maintenance following up.”
Stronger entry: “14:20. Field technician J. Smith reported that the Station 4 discharge pressure transmitter indicated 620 psig while the local gauge indicated 705 psig. Controller compared the indication with adjacent pressure points and notified the shift supervisor. Maintenance will investigate the transmitter. Discrepancy remains unresolved at handover; incoming controller to confirm maintenance status.”
The stronger entry preserves the discrepancy, the actions taken, and the outstanding follow-up.
Operational benefit: Complete entries cut down on repeated investigation and time spent tracking down missing information. PHMSA’s FAQ I.02 applies the same standard to records, which should show thoroughness and authenticity. A note that work was completed on a certain date is usually inadequate.
3. Separate observations from assessments
During an abnormal condition, record the readings, alarms, equipment status, and field reports that were available. Then record the assessment and the action taken. For example:
- Observation: Pressure decreased while an unexpected flow imbalance alarm was active.
- Assessment: The cause remained uncertain; a field condition or instrumentation problem was suspected.
- Action: The controller followed the applicable procedure, notified the supervisor, and requested field verification.
Operational benefit: An early explanation can harden into accepted fact as it passes between people. At Marshall, leak detection alarms were attributed to column separation, and that explanation carried forward across shifts. When the evidence is logged separately, the next controller can reassess as new information arrives, and event reviews have more to work with.
4. Treat every handover as a transfer of responsibility
This applies at shift change, during temporary relief, and whenever responsibility for a console or operating area changes hands. Even a quiet shift has information to pass on. A useful handover covers:
- Current operating status and any abnormal conditions
- Equipment outages, system limitations, and inhibited alarms
- Planned maintenance, startups, shutdowns, or field work
- Upstream or downstream conditions affecting operations
- Required follow-up and who owns it
The incoming controller should have the chance to ask questions and acknowledge the transfer.
Operational benefit: A deliberate handover keeps the incoming controller from having to rediscover the operating picture. PHMSA’s CRM FAQs apply handover requirements to uneventful shifts (C.10), day-only schedules (C.11), and periods when the control room is unattended (B.02). The Third Edition broadens turnover content to any event that could directly or indirectly affect operations. Inspectors check for handover records, and PHMSA has cited handovers that were unsigned or unacknowledged and shift changes kept on spreadsheets instead of the form the operator’s own plan required.
5. Connect field activity with control room awareness
Record communications that affect how the pipeline is monitored or operated, including calibrations, equipment testing, valve work, maintenance, and changes to instrument or communications availability. Note who called, which assets were affected, what coordination occurred, and whether the work is complete.
Log the return to service too. An entry that takes an instrument out of service is incomplete if its restoration is never documented.
Operational benefit: Controllers keep an accurate operating picture, and field work stays coordinated across shifts. The rule requires field personnel to contact the control room when making changes that affect operations, and FAQ F.01 expects operators to document those contacts, including routine work like transmitter calibrations.
6. Carry open items forward until they’re resolved
Pending startups, inspection tools in the line, inhibited alarms, temporary restrictions, and outstanding field verification should stay visible until someone explicitly closes them. Give each a status and a next step, with an owner where appropriate.
Closure should explain the outcome. “Closed” says far less than “Maintenance replaced the transmitter, field and SCADA readings were verified, and the indication was returned to service.”
Operational benefit: At Marshall, the incoming shift lead wasn’t told about the pending startup or the inspection tool in the line. Visible open items keep that kind of context from depending on memory and make follow-up accountable across shifts.
CRMgr, part of the POEMS® CRM Suite, supports structured shift handovers. Controllers document operating events and temporary relief, then generate handover reports from their log entries.
7. Make good logging easy
Consistent categories, practical prompts, and standard fields reduce writing effort while improving completeness. The structure should fit the work, since a temporary relief entry needs different information than an abnormal condition. Free-form narrative still has a place when an event needs explaining.
Review the workflow with controllers. Look for duplicate entry, unclear categories, and fields that don’t help anyone make a decision.
Operational benefit: Logging is part of the controller’s workload, and time spent on it is time away from monitoring. FAQ E.06 counts control manual entries in the workload operators must review each year, and Pipeline Performance Group treats logs as their own category of controller time. Configurable entry menus, like those in CRMgr, help standardize records without adding effort.
8. Use the log to improve the operation
Regular supervisor review can reveal recurring instrument problems, repeated alarm inhibits, unclear procedures, and work that stays open longer than it should. Review should lead to action. If a problem keeps appearing, find out why, assign follow-up, and check whether the fix worked.
Operational benefit: These patterns can guide maintenance priorities, training, procedure updates, and alarm management. FAQ G.02 extends lessons learned to near misses and non-reportable events, much of which first shows up in the log. The record has to be trustworthy for any of this to work. FAQ J.04 accepts electronic records that preserve integrity, authenticity, and date and remain readily retrievable, and FAQ J.01 suggests keeping records at least one year or through the last two periodic tests, whichever is longer.
CRMgr supports log search and supervisor review of controller entries and handover reports, so managers can use the record beyond a single shift.
A simple test
Pick a shift from last month and ask:
- Could someone who wasn’t there understand the operating conditions?
- Could they tell observations from assessments?
- Could they identify the actions taken and their results?
- Could they see what remained open and who owned the follow-up?
If the answers are clear, the log is supporting the operation, and the compliance record is already in place. If not, entry expectations, handover practice, and the logging workflow are the places to start.